MGE Engineering participated in this joint venture contract under the USACE to provide construction support for the Napa River/Napa Creek Flood Protection Project, Contract 2W, including preparation of contract modifications, review and response to Contractor RFI’s, review construction submittals, perform field inspections and site visits. The project included channel widening along the right bank of the Napa River from the Napa Mill Complex upstream approximately 1,600 feet to the First Street Bridge; construction of a soldier pile retaining wall along the bottom edge of the river bank and an upper setback retaining/flood wall with a pedestrian recreation river walk between the two walls, as well as stairs and ramps connecting the upper promenade level behind the setback wall to the lower level between the two walls.